RE: Stagecoach North East Latest News
(Yesterday, 7:45 pm)TransitObserver wrote I’d blame the TVCA for that mess. They wanted the depot fully electric but didn’t invest enough for extra buses. Be interesting if Stockton turn around and say they don’t have enough buses anymore. In my opinion it was a stupid decision to go fully electric all at once. Should have been done in stages, with the final stage being when the new depot was built rather than all at once.
73175/6 where ordered and delivered as Stockton stock - they have been shipped out to other depots purely based on very low amount of vehicles of the road.
Fully electric is working very well - but like everything when you squeeze too hard you cause damage! There are still the same amount of buses needing 28 day inspections, MOT prep - albeit reduced to 2 days.
Any vandalism will now potentially lead to mileage being lost for no bus purely because buses keep being moved to alternative depots!