(19 Nov 2015, 8:37 pm)cbma06 wrote everything within the red box line will be redeveloped, from hylton road roundabout (hylton road roundabout will be gone and replaced by a 4 way traffic system) will be 2 lanes in each direction to b&q roundabout and then still 2 lanes in each direction on the proposed redevelopment site to the new bridge with the new road just bypass the bus depot and go along and under the QA bridge to the new bridge.
http://www.sunderland.gov.uk/PlanDM/StreamDocPage/obj.pdf?DocNo=959810&PDF=true&content=obj.pdf
page 2
Sorry a re-post - my last reply made no sense.
Anyway:
Thanks cbma - i was confused about the area - its good to see they're deciding to change the area around the Queen Alexandrea bridge - although its going to be a nightmare when it starts!, this new road is a good idea, least it'll take the strain off the other roads leading to the new bridge...or will this be the only access to the bridge (sure i read there will be road next to Pallion retail Park leading on to the bridge?)
Hopefully once its completed - the area will open new developments, in all honestly i think the whole area needs it, get rid of everything on the river - which isn't used.
In all honestly this will be a nightmare, the work starts in 2017 - the year where the bridge is nearly complete BUT not quite (with the surrounding roads being closed either temporarily or permanently) - as its expected to be finished in 2018. I would hope that in 2017 - the work will be around Deptford will done... demolishing buildings, if needed etc and so on, then once bridge is completed and opened then work would start at the Queen Alexandrea bridge - replacing the roundabout etc...
I think the work will go ahead for these changes to the area, i just hope the council don't keep delaying it! (remember this is only the planning stages!)
I don't see a page 2 on the link.
-----------------
Anyone wondering here is the timeline for the new bridge work (from this year)
May 2015 - Contract awarded and design is underway
July 2015 - Construction work started
October 2015 - Construction work starts in the river
Winter 2015 - 12-month major improvement works start on A1231 Wessington Way
Summer 2016 - Major improvement works start on B1405 European Way in Pallion
Winter 2016 - A-frame pylon sets sail from Belgium and is lifted into place
Summer 2017 - Bridge deck work is complete
Spring 2018- New bridge scheduled to open
------------------------------
Work for Sunderland Strategic Transport Corridor Phase 3 (The Sunderland Strategic Transport Corridor is a dual carriageway link between the A19 and the Port of Sunderland). (his is the work for the above link where cbma has post)
Phase 3 (SSTC 3) is the critical link in completing the continuous dual carriageway between the A19 and the city centre.
Key Milestones
May 2016 Confirmation of final route
2016 Planning approval
2017 Contractor announced
2017 Works start
2019 Open to traffic