(Yesterday, 3:46 pm)Adrian wrote I really can't understand why they'd order the buses before they have a connection offer and agreed timescales from Northern Powergrid? Isn't it a bit like building a house before having the planning permission.
Down to the way the funding worked, plus I believe the original plan was that the work at the depot would be completed well before now, but as others have posted there are issues nationally and that has pushed back the installation time.